6-14 TECHNICAL REPORT – CALICO SILVER PROJECT Pan American Estimate Pan American (2013) generated an internal resource estimate in 2013 that was based on the results of their 2012 RC drill program (234 holes, representing 56,486 ft/17,217 m) and their validation of historical ASARCO drilling data. Key points: 6-14 TECHNICAL REPORT – CALICO SILVER PROJECT Pan American Estimate Pan American (2013) generated an internal resource estimate in 2013 that was based on the results of their 2012 RC drill program (234 holes, representin; Although the historical mineral resource estimates and feasibility studies completed on the Project provide a wealth of background information, these studies cannot be used to give an accurate estimation of profitability; Recommendations Future work is recommended to be undertaken as a phased approach focused on acquiring additional information necessary for increased resource confidence at Langtry and for the eventual development of a PF; The result of this work was an 6-15 TECHNICAL REPORT – CALICO SILVER PROJECT Inferred silver mineral resource of 58.1 Mt at a grade of 89 g/t Ag for a total of 166 Moz for the Calico Project as a whole; Production figures were based off a report conducted by ASARCO, September 1967, showing an ore reserve of 30,067,000 tons and containing an average of 2.94 ounces of silver per ton; Future work is recommended to be undertaken as a phased approach focused on acquiring additional information necessary for increased resource confidence at Langtry and for the eventual development of a PFS at Waterloo. This brief is based on the cited source artifact and is intended as a research entry point, not a replacement for the original source or EGM canonical data tables.
Source Notes
6-14 TECHNICAL REPORT – CALICO SILVER PROJECT Pan American Estimate Pan American (2013) generated an internal resource estimate in 2013 that was...
Extractive summary evidence · source
Although the historical mineral resource estimates and feasibility studies completed on the Project provide a wealth of background information, these studies cannot...
Extractive summary evidence 2 · source
Recommendations Future work is recommended to be undertaken as a phased approach focused on acquiring additional information necessary for increased resource confidence...
Extractive summary evidence 3 · source
The result of this work was an 6-15 TECHNICAL REPORT – CALICO SILVER PROJECT Inferred silver mineral resource of 58.1 Mt at...
Extractive summary evidence 4 · source
Extracted Document Text
This is a readable excerpt of the EGM normalized Markdown text. It helps search engines and researchers understand PDF, filing, or company-document content while the original source remains authoritative.
# NI 43-101 - October 16, 2025 Source: https://apollosilver.com/wp-content/uploads/2025/10/technical_report_apollo_101625.pdf Fetched: 2026-09-12T06:59:01.681+00:00 Source artifact: 0d928581-98e3-4f15-8f1f-3c1fe52cf8b2 Normalizer input: text ## Content # NI 43-101 - October 16, 2025 NI 43-101 Technical Report and Mineral Resource Estimate for the Calico Silver Project, San Bernardino County, California, USA Submitted to: Apollo Silver Corp. Report Date: October 16, 2025 Effective Date: June 30, 2025 Stantec Consulting International LLC 2890, East Cottonwood Parkway Ste. 300, Salt Lake City, Utah 84121-7283 Tel: (801) 617-3200 Author(s): Derek Loveday, P. Geo. Mariea Kartick, P. Geo. Johnny Marke, PG Project No. 182925562 IMPORTANT NOTICE This notice is an integral component of the Technical Report and Mineral Resource Estimate for the Calico Silver Project, San Bernardino County, California, USA (“Technical Report” or “Report”) and should be read in its entirety and must accompany every copy made of the Technical Report. The Technical Report has been prepared in accordance with the requirements of National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”). The Technical Report has been prepared for Apollo Silver Corp. (“Apollo”) by Stantec Consulting International LLC (“Stantec”). The Technical Report is based on information and data supplied to Stantec by Apollo. The quality of information, conclusions, and estimates contained herein are consistent with the level of effort involved in the services of Stantec, based on i) information available at the time of preparation of the Report, and ii) the assumptions, conditions, and qualifications set forth in this Report. Each portion of the Technical Report is intended for use by Apollo subject to the terms and conditions of its contract, (dated March 13, 2025) with Stantec. Except for the purposes legislated under Canadian provincial and territorial securities law, any other uses of the Technical Report, by any third party, is at that party’s sole risk. The results of the Technical Report represent forward-looking information. The forward-looking information includes pricing assumptions, sales forecasts, projected capital and operating costs, mine life and production rates, and other assumptions. Readers are cautioned that actual results may vary from those presented. The factors and assumptions used to develop the forward-looking information, and the risks that could cause the actual results to differ materially are presented in the body of this Technical Report. Stantec has used their experience and industry expertise to produce the estimates in the Technical Report. Where Stantec has made these estimates, they are subject to qualifications and assumptions, and it should also be noted that all estimates contained in the Technical Report may be prone to fluctuations with time and changing industry circumstances. CERT-1 CERTIFICATE OF QUALIFICATIONS I, Derek J. Loveday, P.Geo., do hereby certify that: 1. I am currently employed as a Geologic Services Manager by Stantec Consulting International LLC, 2890 East Cottonwood Parkway Suite 300, Salt Lake City UT 84121-7283. 2. I graduated with a Bachelor of Science Honors Degree in Geology from Rhodes University, Grahamstown, South Africa in 1992. 3. I am a licensed Professional Geoscientist in the Province of Alberta, Canada, #159394. 4. I have worked as a geologist for a total of thirty-one years since my graduation from university, both for mining and exploration companies and as a consultant specializing in resource evaluation for precious metals and industrial minerals. I have many years of experience with exploring and modelling stratiform polymetallic precious and base metals deposits located in the United States and Mexico. 5. I have read the definition of “Qualified Person” set out in National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI-43-101”) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101), and past relevant work experience, I meet the requirements to be a “Qualified Person” (or “QP”) for the purposes of NI 43-101. 6. I am responsible for the preparation of portions of sections 1 and 2, sections 3 to 24, portions of section 25, section 26 and portions of section 27 of the report titled “NI 43-101 Technical Report for the Mineral Resource Estimate of the Calico Silver Project, San Bernardino County, California, USA” (the “Technical Report”) dated October 16, 2025, with an Effective Date June 30, 2025. 7. I have read NI 43-101 and Form 43-101F1, and the Technical Report has been prepared in compliance with that instrument and form. 8. I was Author and QP of the prior Technical Report prepared for the Calico Silver Project dated April 20, 2023, with Effective Date of February 8, 2023. 9. In 2021, I inspected the Calico Silver Project area from December 13, 2021, through December 14, 2021. 10. At the Effective Date of the Technical Report, to the best of my knowledge, information, and belief, the Technical Report contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading. 11. I am not aware of any material fact or material change with respect to the subject matter of the Technical Report that is not reflected in the Report, the omission to disclose which makes the Report misleading. 12. I am independent of the issuer applying all of the tests in Section 1.5 of NI 43-101. “Original Signed and Sealed by Author” Dated October 16, 2025 _________________________________ Derek J. Loveday, P.Geo. Geologic Services Manager CERT-2 CERTIFICATE OF QUALIFICATIONS I, Mariea Kartick, P. Geo., do hereby certify that: 1. I am currently employed as a Project Manager by Stantec Consulting International LLC, 1560 Broadway Suite 1800 Denver CO 80202-6000. 2. I graduated with an Honours Bachelor of Science degree from the University of Toronto in 2014, and a Master of Science degree from the University of Toronto in 2015. 3. I am a member in-good-standing of the Association of Professional Geoscientists of Ontario (Member 3226) since February 24, 2020. 4. I have worked as a Geologist for 8 years following graduation from my undergraduate degree, both for mining operations and as a consultant, specializing in resource geology for precious and semi- precious metals. I have several years experience writing about and evaluating mineral resources under stringent supervision of experienced QPs. 5. I have read the definition of “Qualified Person” set out in National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“Ni-43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101), and past relevant work experience, I meet the requirements to be a “Qualified Person” (or “QP”) for the purposes of NI 43-101. 6. I am responsible for the preparation of portions of sections 1, 2, 12, 25 and 27 report titled “NI 43- 101 Technical Report for the Mineral Resource Estimate of the Calico Silver Project, San Bernardino County, California, USA” (the “Technical Report”) dated October 16, 2025, and with an Effective Date June 30, 2025. 7. I have read NI 43-101 and Form 43-101F1, and the Technical Report has been prepared in compliance with that instrument and form. 8. I inspected the Waterloo Property between May 16 and May 19, 2022. 9. I have no prior involvement with the Property that is the subject to this Technical Report. 10. At the effective date of the Technical Report, to the best of my knowledge, information, and belief, the Technical Report contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading. 11. I am not aware of any material fact or material change with respect to the subject matter of the Technical Report that is not reflected in the Report, the omission to disclose which makes the Report misleading. 12. I am independent of the issuer applying all of the tests in Section 1.5 of NI 43-101. Dated October 16, 2025 “Original Signed and Sealed by Author” __________________________________ Mariea Kartick, P.Geo. Project Manager T0C-3 CERTIFICATE OF QUALIFICATIONS I, Johnny Marke, PG, do hereby certify that: 1. I am currently employed as a Resource Geologist by Stantec Consulting International LLC, 1001 Lakeside Ave E Ste 1600, Cleveland, Ohio 44114-1193. 2. I graduated with a Bachelor of Science Degree in Geology from The University of Akron, Akron, Ohio in 2019. 3. I am a licensed Professional Geologist in the State of Oregon, #G2896. 4. I have worked as a geologist for a total of six years since my graduation from university, both for mining companies and as a consultant specializing in resource evaluation for precious metals and industrial minerals. I have six years of experience with exploring and modelling stratiform polymetallic precious and base metals deposits located in the United States. 5. I have read the definition of “Qualified Person” set out in National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101), and past relevant work experience, I meet the requirements to be a “Qualified Person” (or “QP”) for the purposes of NI 43-101. 6. I am responsible for the preparation of portions of Sections 1, 2, and 12, Section 14, portions of Sections 25 and 27 of the report titled “NI 43-101 Technical Report for the Mineral Resource Estimate of the Calico Silver Project, San Bernardino County, California, USA” (the “Technical Report”) dated October 16, 2025, with an Effective Date June 30, 2025. 7. I have read NI 43-101 and Form 43-101F1, and the Technical Report has been prepared in compliance with that instrument and form. 8. I inspected the Calico Silver Project area from November 8, 2022, through November 11, 2022. 9. I have no prior involvement with the Property that is the subject to this Technical Report. 10. At the Effective Date of the Technical Report, to the best of my knowledge, information, and belief, the Technical Report contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading. 11. I am not aware of any material fact or material change with respect to the subject matter of the Technical Report that is not reflected in the Report, the omission to disclose which makes the Report misleading. 12. I am independent of the issuer applying all of the tests in Section 1.5 of NI 43-101. “Original Signed and Sealed by Author” Dated October 16, 2025 _________________________________ Johnny Marke, PG Resource Geologist T0C-4 TABLE OF CONTENTS EXECUTIVE SUMMARY ..............................................................................................1-1 INTRODUCTION ..........................................................................................................2-1 2.1 Site Inspection and Author ................................................................................2-1 2.2 Sources of Information ......................................................................................2-2 2.3 Units of Measure ...............................................................................................2-2 RELIANCE ON OTHER EXPERTS ..............................................................................3-1 PROPERTY DESCRIPTION AND LOCATION .............................................................4-1 4.1 Description and Location...................................................................................4-1 4.2 Tenure, Agreements and Royalties ...................................................................4-1 Waterloo Property .................................................................................4-1 Langtry Property . [Excerpt trimmed for readability. Open the original source for the complete filing or document.]