Table 5 | Okvau Ore Reserve Estimate - March 2021 Okvau March 2021 Ore Reserve Estimate Tonnage Grade Contained (Mt) (g/t Au) Au (Koz) Probable Ore Reserve 14.26Mt 1.98g/t Au 907koz Okvau Gold Project | Resource Growth The DFS for the Okvau Gold Project only considered an open pit mining operation. Key points: Table 5 | Okvau Ore Reserve Estimate - March 2021 Okvau March 2021 Ore Reserve Estimate Tonnage Grade Contained (Mt) (g/t Au) Au (Koz) Probable Ore Reserve 14.26Mt 1.98g/t Au 907koz Okvau Gold Project | Resource Growth T; A summary of throughput and mill availability since reaching a steady state of production is as follows: Table 2 | Okvau Processing Statistics Sep 2021 Oct 2021 Nov 2021 Dec 2021 Ore milled annualised 2,199,000t 2,242,00; Emerald has undertaken a drilling program to test the extensions with an aim to grow the resource delineated by the DFS; Project Finance Funding and Debt facility The Company has signed a Credit Agreement with Sprott Private Resource Lending II (Collector), LP (‘Sprott’) for a US$60 million Project finance facility (‘Facility’) for the dev; All-In Sustaining Costs (‘AISC’) for this period was also within guidance at $740 per ounce; With the positive reconciliation and additional throughput as highlighted below, the operation is expected to achieve an annualised AISC per ounce of US$720 to US$780/oz for the remainder of the financial year. This brief is based on the cited source artifact and is intended as a research entry point, not a replacement for the original source or EGM canonical data tables.
Source Notes
Table 5 | Okvau Ore Reserve Estimate - March 2021 Okvau March 2021 Ore Reserve Estimate Tonnage Grade Contained (Mt) (g/t Au)...
Extractive summary evidence · source
A summary of throughput and mill availability since reaching a steady state of production is as follows: Table 2 | Okvau Processing...
Extractive summary evidence 2 · source
Emerald has undertaken a drilling program to test the extensions with an aim to grow the resource delineated by the DFS.
Extractive summary evidence 3 · source
Project Finance Funding and Debt facility The Company has signed a Credit Agreement with Sprott Private Resource Lending II (Collector), LP (‘Sprott’)...
Extractive summary evidence 4 · source
Extracted Document Text
This is a readable excerpt of the EGM normalized Markdown text. It helps search engines and researchers understand PDF, filing, or company-document content while the original source remains authoritative.
# Half Year Report 2021 Source: https://www.emeraldresources.com.au/wp-content/uploads/2023/09/2022-16-Mar-Interim-Report-31-December-2021.pdf Published: 2022-03-16T00:00:00+00:00 Fetched: 2026-05-12T14:52:59.853+00:00 Source artifact: f0a56c95-7ce0-4b2a-9fec-66f9a34b8e80 Normalizer input: text ## Content # Half Year Report 2021 ABN 72 009 795 046 Interim Report 31 December 2021 HALF-YEAR REPORT 31 DECEMBER 2021 Contents Corporate Directory 3 Auditor’s Independence Declaration 4 Directors’ Report 5 Interim Financial Statements 21 Directors’ Declaration 36 Independent Auditor’s Review Report 37 Emerald Resources NL | 2 CORPORATE DIRECTORY Non-Executive Chairman Simon Lee AO Managing Director Morgan Hart Executive Director Michael Evans Non-Executive Directors Ross Stanley Billie Jean Slott Mark Clements Company Secretary Mark Clements Principal & Registered Office 1110 Hay Street West Perth WA 6005 Telephone: +61 8 9286 6300 Facsimile: +61 8 6243 0032 Share Registry Automic Group Level 5, 191 St Georges Terrace PERTH WA 6000 Telephone: 1300 288 664 Auditors HLB Mann Judd (WA Partnership) Level 4, 130 Stirling Street PERTH WA 6000 Bankers National Australia Bank 50 St Georges Terrace PERTH WA 6000 Macquarie Bank Limited Level 23, 240 St Georges Terrace PERTH WA 6000 Solicitors Steinepreis Paganin 16 Milligan Street PERTH WA 6000 Norton Rose Fulbright 108 St Georges Terrace PERTH WA 6000 Securities Exchange Listing Australian Securities Exchange (Home Exchange: Perth, Western Australia) Code: EMR Website Address www.emeraldresources.com.au Emerald Resources NL | 3 AUDITOR’S INDEPENDENCE DECLARATION As lead auditor for the review of the consolidated financial report of Emerald Resources NL for the half-year ended 31 December 2021, I declare that to the best of my knowledge and belief, there have been no contraventions of: a) the auditor independence requirements of the Corporations Act 2001 in relation to the review; and b) any applicable code of professional conduct in relation to the review. Perth, Western Australia L Di Giallonardo 16 March 2022 Partner Emerald Resources NL | 4 DIRECTORS’ REPORT Your directors present their report on the consolidated entity (or ‘Group’) consisting of Emerald Resources NL (‘Emerald’ or the ‘Company’) and the entities it controlled at the end of, or during, the half-year ended 31 December 2021. Directors The following persons were directors of Emerald during the half-year and up to the date of this interim report unless otherwise stated: Simon Lee AO Non-Executive Chairman Morgan Hart Managing Director Michael Evans Executive Director Mark Clements Non-Executive Director Billie Jean Slott Non-Executive Director (appointed 5 October 2021) Ross Stanley Non-Executive Director Review of Operations Operating Result During the half-year the Company recorded a profit after tax of $11.876m (31 December 2020: loss of $(8.083m)). This included a fair value loss on the embedded derivative of $(7.040m) (31 December 2020: gain of $3.724m) finance costs of $8.263m (31 December 2020: $0.074m) and a net foreign exchange gain of $2.046m (31 December 2020: loss of $(7.662m)). The Group’s net asset position improved from $105m at 30 June 2021 to $141m as at 31 December 2021. Okvau production statistics summary A summary of production statistics for Okvau since full commercial production was achieved in September 2021 is contained in the following table. Table 1 | Okvau Production Statistics 4 months to 31 December 2021 OP mining Total movement BCM ‘000 1,963 Strip ratio w:o 3.86 Ore mined kt 1,465 Mined grade g/t 1.54 Contained gold oz 72,719 Processing Ore milled kt 750 Head grade g/t 2.07 Recovery % 73.4 Gold produced oz 36,626 Gold poured oz 33,326 Gold sold oz 29,000 Cambodian Gold Projects Overview Emerald is a developer and explorer of gold projects. In particular, Emerald has been focused on the development and commissioning of its most advanced project, the Okvau Gold Mine in Cambodia which saw first production in June 2021 and a steady state of production in September 2021. Since production commenced in June 2021, Emerald has now poured over 60,000 ounces of gold from its operations. Emerald also hold a number of other projects in Cambodia which are made up of a combination of granted mining licences (100% owned by Emerald), and interests in joint venture agreements. Together, Emerald’s interest in its Cambodian Projects covers a combined area of 1,239km2. Okvau Gold Mine The Okvau Gold Mine is the most advanced of Emerald’s projects. The Okvau Gold Mine is located approximately 275km north-east of Cambodia’s capital city of Phnom Penh in the province of Mondulkiri (refer Figures 1 and 2). The town of Kratie is located on the Mekong River approximately 90km to the west and the capital of Mondulkiri, Saen Monourom is located approximately 60km to the south-east. Emerald Resources NL | 5 DIRECTORS’ REPORT Review of Operations (continued) The consolidated entity successfully completed the development of Emerald’s 100% owned Okvau Gold Mine in the June 2021 financial year. This culminated in its maiden gold pour after successfully commissioning the processing plant and gold room as announced on 26 June 2021. During the current period, commissioning activities continued on the sulphide float regrind circuit which was successfully completed in July 2021. This marked the practical completion of the Okvau Gold Mine commissioning process and commencement of normal run of mine operations. Following the successful commissioning of the processing plant and commencement of production, Emerald has now poured over 2,000kgs of gold bullion from its operations with a total of approximately US$111 million of gold doré to the date of this report. Figure 1 | Cambodian Gold Project | Location Figure 2 | Cambodian Gold Project | Exploration Licence Areas Okvau Gold Mine Operating Overview Following commissioning activities and achieving a steady state of production in September 2021, the Okvau Gold Mine achieved guidance producing 26,395 ounces for the December 2021 quarter. All-In Sustaining Costs (‘AISC’) for this period was also within guidance at $740 per ounce. With the positive reconciliation and additional throughput as highlighted below, the operation is expected to achieve an annualised AISC per ounce of US$720 to US$780/oz for the remainder of the financial year. Okvau Gold Mining Activity Mining operations during the period continued advancing the Stage 1 Pit design, targeting fresh sulphide ore. Lesser mining of waste from Stage 2 and Stage 3 allowed for the required ancillary infrastructure to be constructed during the dry season at Okvau. Mining continues to remain marginally ahead of schedule and in line with milling requirements. Actual fresh sulphide ore mined to date of 1,687kt @ 1.66g/t for 90,158oz (lower cut 0.5g/t), reconciles positively against reserve (+21%) against 1,169kt @ 1.97g/t for 74,569oz (lower cut 0.625g/t). The positive reconciliation has continued to allow the Company the flexibility of preferentially milling the highest-grade ore zones whilst still building a substantial +1g/t stockpile (+556kt). Total surveyed movement for the quarter was 2,904,208 BCM of ore and waste against a scheduled 2,700,000 BCM with 2,419,450 BCMs blasted. Emerald Resources NL | 6 DIRECTORS’ REPORT Review of Operations (continued) Figure 3 | Okvau Gold Mine Open Pit Processing Since achieving practical completion and reaching a steady state of production in September 2021, the process plant has run consistently above nameplate of 2.0Mtpa and is now achieving a throughput rate +10% above DFS target. A summary of throughput and mill availability since reaching a steady state of production is as follows: Table 2 | Okvau Processing Statistics Sep 2021 Oct 2021 Nov 2021 Dec 2021 Ore milled annualised 2,199,000t 2,242,000t 2,204,000t 2,327,000t (DFS: 2.0Mtpa) Milling rate (DFS: 250tph) 266tph 266tph 264tph 273tph Availability (DFS: 91.3%o) 94.2% 96.2% 95.3% 97.3% Sulphide ore gold recoveries were compromised during the second half of the period, in particular milling during October and November achieved lower than budgeted gold recoveries attributed to elevated organic carbon in circuit emanating from the early reclamation of processing water from the tailings dam and grind size compromises related to transportation delays on critical spares and wear parts for the processing plants fine grind HIG mill. In both cases, organic carbon and critical spares supply issues were resolved late in November with strong December production (continuing subsequent to period end). The strong December production and recoveries enabling the Company to meet production and cash cost forecasts for the December 2021 quarter. The organic carbon issue has been resolved in the process plant with modifications to the carbon regeneration and operating parameters, changes to the specification of HIG mill liners and advanced supply of inventory which has resolved the compromised fine grind circuit performance in December 2021. Gold Production Gold production since commissioning on oxide ore in June 2021 (inclusive of gold in circuit) is 49,406 ounces to the end of the period. This includes production for the December 2021 quarter of 26,395 ounces, which compares well and confirms the suitability of all plant for +100,000 ounce per annum gold production. Gold poured during the period totalled 41,173 ounces. During the period, shipments totalling 35,923 ounces of gold have been received by the refinery with outturns received. Nineteen of the twenty shipments have been sold during the period at an average price of US$1,786 per ounce. A further 6,117 ounces of gold doré has been poured ahead of refinery outturn. Emerald Resources NL | 7 DIRECTORS’ REPORT Review of Operations (continued) Operating Physicals A summary of operating physicals since reaching a steady state of production is as follows: Table 3 | Okvau Operating Physicals Sep 2021 Oct 2021 Nov 2021 Dec 2021 Ore mined (‘000 BCM) 137 113 115 124 Waste mined (‘000 BCM) 267 412 390 405 Stripping ratio (waste:ore) 1.96 3.65 3.41 3.28 Ore mined (‘000 t) 376 322 399 434 Ore milled (‘000 t) 181 190 181 197 Head grade (g/t) 2.16 1.97 1.64 2.48 Recovery (%) 81.7% 66.4% 60.1% 80.4% Gold production (oz) 10,231 8,009 5,736 12,650 Operational Outlook Gold production guidance at the Okvau Gold Mine remains in line with the DFS of 100,000oz to 110,000oz on an annualised basis. Production guidance for the remainder of FY2022 remains in line with DFS forecasts at 25-30,000/oz per quarter and cash costs of US$720 – US$780/oz. Okvau Gold Mine Mineral Resources and Reserves Estimates Table 4 | Okvau Mineral Resource Estimate – March 2021 Okvau March 2021 Mineral Resource Estimate Indicated Resources Inferred Resources Total Resources Cut-off Tonnage Grade Contained Tonnage Grade Contained Tonnage Grade Contained (Au g/t) (Mt) (g/t Au) Au (Koz) (Mt) (g/t Au) Au (Koz) (Mt) (g/t Au) Au (Koz) 0.70 15.11 2.08 1,008 2.57 1.61 133 17.68 2.01 1,141 The DFS delivered a maiden Ore Reserve (Probable) estimate of 14.26Mt @ 1.98g/t Au for 907,000 ounces gold (refer Table 5). Table 5 | Okvau Ore Reserve Estimate - March 2021 Okvau March 2021 Ore Reserve Estimate Tonnage Grade Contained (Mt) (g/t Au) Au (Koz) Probable Ore Reserve 14.26Mt 1.98g/t Au 907koz Okvau Gold Project | Resource Growth The DFS for the Okvau Gold Project only considered an open pit mining operation. The Okvau Deposit remains ‘open’ at depth with high grade shoots providing longer term underground potential. High grade resources have been defined immediately below the floor of the final pit design (refer Figure 4). Emerald Resources NL | 8 DIRECTORS’ REPORT Review of Operations (continued) Figure 4 | Okvau Resource Growth | Depth Extensions Some of the highest grade intersections sit beneath the open pit floor. Deep diamond core holes have been drilled to test for strike and down dip continuity of h [Excerpt trimmed for readability. Open the original source for the complete filing or document.]