Briefing
Silver Ore Reserves have been increased to 47.9Mt at 60.8 g/t Ag for For personal use only 93.5Moz with 91% of the Project revenue expected to be derived from silver.1 The initial stage 1 of the proposed development will focus on a subset of the Life of Mine (LOM) plan containing 29.9Mt at 68 g/t Ag for 65.4Moz, over a 16-year period with a low strip ratio of 1.47:1.0 (waste:ore).1 A second stage supported by pre-fea Key points: Silver Ore Reserves have been increased to 47.9Mt at 60.8 g/t Ag for For personal use only 93.5Moz with 91% of the Project revenue expected to be derived from silver.1 The initial stage 1 of the proposed development will; Silver Mines Limited ABN: 45 107 452 942 Page 4 The financial model developed for the Project based on the 2026 LOM plan indicates a total operating margin of A$2.39 billion, with project payback 3.0 years from the comme; The information in this report that relates to Production Targets has been extracted from the Company's ASX Announcement Bowdens Definitive Feasibility Study Confirms Robust Economics as Reserves Lift to 93.5Moz of Silve; Highlights of the 219 samples taken in this program include 1960 g/t Ag (sample No 339705), 435 g/t Ag (sample No 339725) and 340 g/t Ag (sample No 339847).7 Barite highlights include greater than 44.8% (sample No 339702; It is now anticipated that DPHI will assess the submission material enabling it to provide an updated assessment report to 1 Silver Mines Limited (ASX:SVL) release: Bowdens Definitive Feasibility Study Confirms Robust Ec; As a result, while the combined LOM financial metrics (Tables 1 and 3 Silver Mines Limited (ASX:SVL) release Exploration Update on Californian Silver & Gold Assets dated 16 April 2026. This brief is based on the cited source artifact and is intended as a research entry point, not a replacement for the original source or EGM canonical data tables.
Source Notes
Silver Ore Reserves have been increased to 47.9Mt at 60.8 g/t Ag for For personal use only 93.5Moz with 91% of the...
Extractive summary evidence · source
Silver Mines Limited ABN: 45 107 452 942 Page 4 The financial model developed for the Project based on the 2026 LOM...
Extractive summary evidence 2 · source
The information in this report that relates to Production Targets has been extracted from the Company's ASX Announcement Bowdens Definitive Feasibility Study...
Extractive summary evidence 3 · source
Highlights of the 219 samples taken in this program include 1960 g/t Ag (sample No 339705), 435 g/t Ag (sample No 339725)...
Extractive summary evidence 4 · source
Extracted Document Text
This is a readable excerpt of the EGM normalized Markdown text. It helps search engines and researchers understand PDF, filing, or company-document content while the original source remains authoritative.
# Silver Mines Limited June 2026 Quarterly Activities Report Source: https://www.silvermines.com.au/wp-content/uploads/2026/09/07285883l33460.pdf Published: 2026-07-31T00:00:00+00:00 Fetched: 2026-09-12T08:15:37.321+00:00 Source artifact: 8baecbbc-deb4-47c1-a4d0-0877adc975a6 Normalizer input: text ## Content # Silver Mines Limited June 2026 Quarterly Activities Report Source: https://www.silvermines.com.au/wp-content/uploads/2026/09/07285883l33460.pdf Published: 2026-07-31 Level 28, 88 Phillip St Sydney NSW 2000 P: +61 2 8316 3997 F: +61 2 8316 3999 Info@silvermines.com.au www.silvermines.com.au 31 July 2026 ACTIVITIES REPORT FOR THE QUARTER ENDED 30 June 2026 ( Quarter HIGHLIGHTS Definitive Feasibility Study, Life of Mine Plan, Ore Reserves and Mineral Resource Estimate Subsequent to the Quarter, the Company announced a DFS which positions the Bowdens Silver Project ( ) as one of the world's premier undeveloped silver projects. Silver Ore Reserves have been increased to 47.9Mt at 60.8 g/t Ag for For personal use only 93.5Moz with 91% of the Project revenue expected to be derived from silver.1 The initial stage 1 of the proposed development will focus on a subset of the Life of Mine (LOM) plan containing 29.9Mt at 68 g/t Ag for 65.4Moz, over a 16-year period with a low strip ratio of 1.47:1.0 (waste:ore).1 A second stage supported by pre-feasibility study level works, subject to approvals, is expected to ultimately result in mining and processing of the remaining 18.3Mt for a total mine operational life of 26 years with a LOM strip ratio of 1.69:1.0.1 Subsequent to the Quarter, the Company also announced an updated Mineral Resource Estimate ( ) and updated Ore Reserves.1 Ore Reserves total 47.9 million tonnes at 60.8 g/t silver, 0.36% zinc and 0.26% lead for an increase of 46% to the ore tonnes relative to the 2024 Ore Reserve estimate with an A$30 per tonne NSR cut off.1 The contained silver in Ore Reserves has increased by 30% to 93.5 million ounces and silver is now forecast to contribute around 91% of the revenue in the mine plan, up from 85% in the 2024 Ore Reserves estimate.1 The 2026 MRE above 25g/t AgEq2 cut-off grade reflects additional drilling (including a further 2,248 assays from 2,265m drilled), updated geological domains, improved metallurgy and changes to metal pricing assumptions. Bowdens Silver Project, New South Wales The Company continues to pursue the redetermination of the BSP through the NSW Department of Planning Housing and Infrastructure ( ) planning approvals system. The Company has submitted an updated Biodiversity Development Assessment Report for the Bowdens Project along with an associated response to DPHI relating to Requests for Information. It is now anticipated that DPHI will assess the submission material enabling it to provide an updated assessment report to 1 Silver Mines Limited (ASX:SVL) release: Bowdens Definitive Feasibility Study Confirms Robust Economics as Reserves Lift to 93.5Moz of Silver dated 21 July 2026. 2 Refer Notes on Resource Table 4 for AgEq calculations. Silver Mines Limited ABN: 45 107 452 942 Page 1 the Independent Planning Commission of NSW for consideration and subsequent DA redetermination. The Company also announced the acquisition of strategic parcel of land adjacent to its Bowdens Silver Project and associated water entitlements. The acquisition provides the Company with numerous benefits including enhanced project water security, additional biodiversity enhancement opportunities, together with potential employee housing and infrastructure development options. Calico North Project and Kramer Hills Farm-In The Company announced that a rock chip and field mapping program at Calico North was completed. For personal use only Of 219 rock chips, 41 contained more than 50 g/t Ag and 21 more than 100 g/t Ag, including samples 339705, 339725 & 339847 returning assays of 1,960 g/t Ag, 435 g/t Ag & 340 g/t Ag, respectively.3 Silver and barite, Critical Minerals in the US, were confirmed by the mapping and rock chip sampling program with best barite assays including samples 339702, 339749, 339652 returning assays of over 44.8% Ba (over detection limit), 44.3% Ba & 41.8% Ba respectively.3 Phase one drill planning is underway for both projects. Corporate $7.98 million was raised via the exercise of outstanding unlisted options. Bowdens Silver Project DFS, Ore Reserves and MRE On 21 July 2026, Silver Mines Limited ( Silver Mines or the Company ) announced a Definitive Feasibility Study ( ) for the Bowdens Silver Project ( Project ). The Company also announced an updated Mineral Resource Estimate ( 2026 MRE ) and Ore Reserve Estimate ( 2026 Reserves ) for the BSP. DFS and LOM Summary The DFS for the BSP has resulted in significant improvements to the economic parameters of the Project. The Bowdens Ore Reserve Estimate will require a staged development. The DFS for the BSP specifically references a 29.9Mt ore mine design, which is less than the 2026 Life of Mine Design ( ) design which contains 48.2Mt ore. The DFS mine design only includes Stage 1 and has been intentionally limited in scale to match the Stage 1 tailings landform which has been designed to hold 30Mt of filtered tailings. Stage 2 (which includes the additional 18.3Mt for the total 48.2Mt 2026 LOM Plan) requires a Stage 2 filtered tailings landform, all other mine infrastructure is the same as the DFS. The design of the Stage 2 filtered tailings landform is at pre-feasibility study level only. All other aspects of the 2026 LOM design are at DFS level. As a result, while the combined LOM financial metrics (Tables 1 and 3 Silver Mines Limited (ASX:SVL) release Exploration Update on Californian Silver & Gold Assets dated 16 April 2026. Silver Mines Limited ABN: 45 107 452 942 Page 2 2, "LOM Stage 1 and 2 Development" columns) reflect the full 26-year mine plan, investors should note that the Stage 2 component carries a higher level of uncertainty consistent with its pre-feasibility study status. The updated studies for the BSP have demonstrated strong economics and significant improvements to the Optimisation Study ( 2024 Study ) from December 2024.4 The key economics of the BSP from the DFS and 2026 LOM are set out in Table 1 below: Table 1: Bowdens Silver Project Economic Parameters Parameter Unit 2024 Study DFS LOM Difference Difference (Dec 2024) Stage 1 Stage 1 and 2 (DFS vs 2024 (LOM vs 2024 Development Developments Study) Study) (Jul 2026) (Jul 2026) Stage 1 Stage 1 and 2 For personal use only Development Developments Processing Plant, Infrastructure and Sustaining Capital Process Plant (2.0Mtpa) A$m 93.8 180.5 180.5 +92% +92% Non-Processing Infrastructure A$m 122.1 113.3 113.3 -7% -7% Other A$m 78.6 107.8 107.8 +37% +37% Indirect A$m 37.1 52.9 52.9 +42% +42% Total (including contingency) A$m 332 455 455 +37% +37% Sustaining Capital (LOM) A$m 14.8 23.5 90.8 +52% +513% LOM Capex A$m 346 478 545 +38% +58% Production Summary Life of Mine (LOM) Years 16.0 16.75 26.0 +0.75 years +9.25 years LOM Strip Ratio W:O 1.49 1.47 1.69 -1% +13% Processing Rate Mtpa 2.0 2.0 2.0 n/c n/c LOM Payable Silver Production Moz 50.3 51.1 73.2 +2% +46% LOM Payable Zinc Production Kt 31 27 46 -13% +48% LOM Payable Lead Production kt 56 49 84 -13% +50% LOM Average Silver Production Mozpa 3.7 3.8 3.2 +3% -14% LOM Average Silver Recovery % 82.7 82.8 82.1 +1% -1% LOM Operating Costs 4 Silver Mines Limited (ASX:SVL) release: Optimisation Study Highlights Robust High-Margin Ag Project dated 20 December 2024. Silver Mines Limited ABN: 45 107 452 942 Page 3 Parameter Unit 2024 Study DFS LOM Difference Difference (Dec 2024) Stage 1 Stage 1 and 2 (DFS vs 2024 (LOM vs 2024 Development Developments Study) Study) (Jul 2026) (Jul 2026) Stage 1 Stage 1 and 2 Development Developments Mining (including rehabilitation) A$/t 17.99 19.85 20.37 +10% +13% milled Processing A$/t 20.78 20.73 20.71 0% 0% milled Administrative A$/t 5.65 6.02 6.01 +7% +6% milled For personal use only C1 Costs A$/oz 23.28 26.91 29.75 +16% +28% C1 Costs US$/oz 15.59 18.84 20.82 +21% +34% AISC A$/oz 24.81 29.32 32.91 +18% +33% AISC US$/oz 16.62 20.53 23.04 +24% +39% Project Economics LOM Pre-Tax Operating Margin A$m 948 1,812 2,390 +91% +152% NPV5% (Pre-Tax) A$m 359 877 1,043 +144% +191% NPV5% (Post-Tax) A$m 253 626 736 +147% +191% IRR (Pre-Tax) % 21.0 31.5 31.5 +50% +50% Payback (Post-Tax) Years 3.9 3.0 3.0 -23% -23% Profitability Index (x) 1.76 2.40 2.64 +36% +50% NPV (Pre-Tax) / Pre-Prod Capex (x) 1.08 1.93 2.30 +78% +113% n/c = no change. A number of scoping changes relative to the 2024 Study were made during the DFS. The key changes include: Process flow sheet updated to minimise overgrinding of soft material. Changes include: o Addition of secondary crusher; o Inclusion of fine ore screening after the SAG mill to divert final size material directly to the flotation cells; and o Ability to by-pass fine ore screening when not needed. Tailings filtration methodology changed from a two-step process to a single step process. Optimisation plan included a desliming step with different dewatering methods for the fines and coarse product. DFS plan is to pressure filter the entire tails stream in a single step. Silver Mines Limited ABN: 45 107 452 942 Page 4 The financial model developed for the Project based on the 2026 LOM plan indicates a total operating margin of A$2.39 billion, with project payback 3.0 years from the commencement of production. Project Pre-Tax NPV5 is estimated at A$1.04 billion, with an IRR of 31.5%. Project Post-Tax NPV5 is estimated at $736 million, with an IRR of 26%. Table 2: Bowdens Silver Project Economics Project Economics Parameter Unit 2024 Study DFS LOM Difference Difference (Dec 2024) Stage 1 Stage 1 and 2 (DFS vs 2024 (LOM vs 2024 Development Developments Study) Study) (Jul 2026) (Jul 2026) Stage 1 Stage 1 and 2 Development Developments For personal use only Revenue A$m 2,510 3,538 5,175 +41% +106% Operating Expenses A$m 1,562 1,726 2,785 +10% +78% Operating Margin A$m 948 1,812 2,390 +91% +152% Undiscounted Cash Flow Pre-Tax A$m 631 1,434 1,945 +127% +208% Undiscounted Cash Flow Post-Tax A$m 469 1,056 1,412 +125% +201% NPV5% (Pre-Tax) A$m 359 877 1,043 +144% +190% NPV5% (Post-Tax) A$m 253 626 736 +147% +191% IRR (Pre-Tax) % 21 31.5 31.5 +50% +50% IRR (Post-Tax) % 18 26 26 +44% +44% Payback (Post-Tax) Years 3.9 3.0 3.0 -23% -23% Profitability Index (x) 1.76 2.40 2.64 +36% +50% NPV (Pre-Tax) / Pre-Prod Capex (x) 1.08 1.93 2.30 +78% +113% In terms of product value, under the 2026 LOM plan, the combination of silver and zinc, both of which are included on the NSW Critical Minerals and High-Tech Metals list, account for approximately 95% of revenue from the Bowdens Silver Project. Silver alone contributes more than 91% of revenue from the 2026 LOM plan, making the Bowdens Silver Project one of the most leveraged silver development projects in the world. Please refer to the Company s announcement dated 21 July 2026 for full details regarding the DFS. Ore Reserve The Company, in conjunction with Resolve Mining Solutions, produced a 2026 Reserve for the BSP based on the M & I component of the 2026 MRE, refer to Table 3 and Figure 1. This represents a snapshot of the current economically extractable Resources for a given set of cost and pricing assumptions and modifying factors in accordance with the JORC Code. Silver Mines Limited ABN: 45 107 452 942 Page 5 The Bowdens Silver Ore Reserve is estimated at 47.9 million tonnes at 60.8 g/t silver, 0.36% zinc and 0.26% lead for 93.5 million ounces of silver, 172 kilo-tonnes of zinc and 127 kilo- tonnes of lead in contained metal. Table 3: July 2026 Ore Reserve* Reserve Grades Contained Metal Tonnes Classification Ag (g/t) Zn (%) Pb (%) Ag (Moz) Zn (kt) Pb (kt) (Mt) Proven 44.6 61.7 0.37 0.27 88.5 165 122 Probable 3.3 47.3 0.21 0.15 4.9 7 5 Total 47.9 60.8 0.36 0.26 93.5 172 127 *Notes: 1. Ore Reserves are a subset of Mineral Resources. 2. Ore Reserves confor [Excerpt trimmed for readability. Open the original source for the complete filing or document.]
