STOCKWORK ZONE PRE-FEASIBILITY STUDY AND UNDERGROUND PRELIMINARY ECONOMIC ASSESSMENT OF THE EL TIGRE SILVER-GOLD PROJECT SONORA, MEXICO

Silver Tiger Metals Inc. · SLVR document official

The design of the mine required several steps, as listed below: • Create a diluted block model from the Mineral Resource model; • Complete pit optimization to select the optimal pit shell to be used for the mine design; • Design an operational surface mine (with ramps and benches) based on the optimal pit shell; and • Develop a life-of-mine (“LOM”) production schedule, based on supplying up to 15,000 tonnes of ore pe

Briefing

The design of the mine required several steps, as listed below: • Create a diluted block model from the Mineral Resource model; • Complete pit optimization to select the optimal pit shell to be used for the mine design; • Design an operational surface mine (with ramps and benches) based on the optimal pit shell; and • Develop a life-of-mine (“LOM”) production schedule, based on supplying up to 15,000 tonnes of ore pe Key points: The design of the mine required several steps, as listed below: • Create a diluted block model from the Mineral Resource model; • Complete pit optimization to select the optimal pit shell to be used for the mine design; The cut-off grades applied are as follows: OX = Oxide ore OX-LG = 0.11-0.15 g/t AuEq OX-HG > 0.15 g/t AuEq SU = Sulphide ore SU-LG = 0.16-0.22 g/t AuEq OX-HG > 0.22 g/t AuEq 16.2 MINING SCHEDULE The surface mine producti; Metallurgical Recoveries The El Tigre Project’s process plant cyanide/leach metallurgical recovery assumptions are: Underground mine Ag = 84%, Au = 90% Historical tailings Ag = 83%, Au = 82% Stockpiled mineralization Ag; 481 Based on the above information, hydraulic head of approximately 13.1 m above the VW sensor was measured in drill hole GT-PFS-23-003 and approximately 7.8 m of head above the VW sensor was measured in drill hole GT-PF; These Mineral Reserve tonnages and grades are used as the planning basis for the production schedule; 16.1 MINE PHASING To access higher-grade ore and lower waste stripping quantities early in the production schedule, the pit has been subdivided into three phases. This brief is based on the cited source artifact and is intended as a research entry point, not a replacement for the original source or EGM canonical data tables.

Source Notes

The design of the mine required several steps, as listed below: • Create a diluted block model from the Mineral Resource model;...

Extractive summary evidence · source

The cut-off grades applied are as follows: OX = Oxide ore OX-LG = 0.11-0.15 g/t AuEq OX-HG > 0.15 g/t AuEq SU...

Extractive summary evidence 2 · source

Metallurgical Recoveries The El Tigre Project’s process plant cyanide/leach metallurgical recovery assumptions are: Underground mine Ag = 84%, Au = 90% Historical...

Extractive summary evidence 3 · source

481 Based on the above information, hydraulic head of approximately 13.1 m above the VW sensor was measured in drill hole GT-PFS-23-003...

Extractive summary evidence 4 · source

Extracted Document Text

This is a readable excerpt of the EGM normalized Markdown text. It helps search engines and researchers understand PDF, filing, or company-document content while the original source remains authoritative.

# STOCKWORK ZONE PRE-FEASIBILITY STUDY AND UNDERGROUND PRELIMINARY ECONOMIC ASSESSMENT OF THE EL TIGRE SILVER-GOLD PROJECT SONORA, MEXICO

Source: https://silvertigermetals.com/files/Silver_Tiger_El_Tigre_PFS_PEA_by_PE_20260122.pdf
Fetched: 2026-09-12T07:08:50.056+00:00
Source artifact: 0d00c7f9-718f-4efe-aeae-044824a5100b
Normalizer input: text

## Content

# STOCKWORK ZONE PRE-FEASIBILITY STUDY AND UNDERGROUND PRELIMINARY ECONOMIC ASSESSMENT OF THE EL TIGRE SILVER-GOLD PROJECT SONORA, MEXICO
STOCKWORK ZONE PRE-FEASIBILITY STUDY
AND
UNDERGROUND PRELIMINARY ECONOMIC ASSESSMENT
OF THE
EL TIGRE SILVER-GOLD PROJECT
SONORA, MEXICO
LATITUDE 30°35’15” N, LONGITUDE 109°13’23” W
UTM WGS84 12R 670,380 m E, 3,385,230 m N
FOR
SILVER TIGER METALS INC.
NI-43-101 & 43-101F1
TECHNICAL REPORT
Andrew Bradfield, P.Eng.
Jarita Barry, P.Geo.
Fred H. Brown, P.Geo.
David Burga, P.Geo.
D. Grant Feasby, P.Eng.
Eugene Puritch, P.Eng., FEC, CET
D. Gregory Robinson, P.Eng.
William Stone, Ph.D., P.Geo.
David Salari, P.Eng., D.E.N.M. Engineering Ltd.
James Smith, P.Eng., WSP Canada Inc.
P&E Mining Consultants Inc.,
Report 481
Effective Date: June 20, 2025
Signing Date: January 22, 2026
TABLE OF CONTENTS
1.0 SUMMARY .........................................................................................................................1
1.1 Property, Location, Access ......................................................................................1
1.2 History......................................................................................................................3
1.3 Geology and Mineralization ....................................................................................3
1.4 Exploration and Drilling ..........................................................................................4
1.5 Sampling, Analyses and Data Verification ..............................................................5
1.6 Mineral Processing and Metallurgy .........................................................................5
1.7 Mineral Resource Estimate ......................................................................................7
1.8 Mineral Reserve Estimate ......................................................................................13
1.9 Mining Methods .....................................................................................................14
1.10 Recovery Methods .................................................................................................16
1.11 Project Infrastructure .............................................................................................17
1.12 Market Studies and Contracts ................................................................................19
1.13 Environmental Studies, Permits, and Social or Community Impacts ....................19
1.14 Capital and Operating Costs ..................................................................................20
1.15 Economic Analysis ................................................................................................21
1.16 Risks and Opportunities .........................................................................................23
1.17 Conclusions ............................................................................................................23
1.18 Recommendations ..................................................................................................24
1.19 Preliminary Economic Assessment........................................................................24
1.19.1 Mineral Processing and Metallurgy .....................................................24
1.19.2 Underground Mining Methods ............................................................25
1.19.3 Recovery Methods ...............................................................................26
1.19.4 Project Infrastructure ...........................................................................27
1.19.5 Market Studies and Contracts ..............................................................29
1.19.6 Capital and Operating Costs ................................................................29
1.19.7 Economic Analysis ..............................................................................30
1.19.8 El Tigre North Analysis .......................................................................33
1.19.9 Risks and Opportunities .......................................................................33
1.19.10 Conclusions and Recommendations ....................................................33
2.0 INTRODUCTION AND TERMS OF REFERENCE .......................................................35
2.1 Terms of Reference ................................................................................................35
2.2 Independent Site Visits ..........................................................................................35
2.3 Sources of Information ..........................................................................................36
2.4 Units and Currency ................................................................................................37
3.0 RELIANCE ON OTHER EXPERTS ................................................................................48
4.0 PROPERTY DESCRIPTION AND LOCATION .............................................................49
4.1 Location .................................................................................................................49
4.2 Property Description and Mineral Tenure .............................................................49
4.3 Mexican Mineral Policy .........................................................................................54
4.4 Surface Rights ........................................................................................................55
4.5 Environmental and Permitting ...............................................................................55
4.6 Comments on Section 4 .........................................................................................56
5.0 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND
PHYSIOGRAPHY .............................................................................................................57
P&E Mining Consultants Inc. Page i
Silver Tiger Metals Inc., El Tigre Pre-Feasibility and Preliminary Econonmic Assessment, Report No. 481
5.1 Access ....................................................................................................................57
5.2 Climate ...................................................................................................................57
5.3 Local Resources and Infrastructure .......................................................................58
5.4 Physiography..........................................................................................................60
5.5 Comments on Section 5 .........................................................................................60
6.0 HISTORY ..........................................................................................................................61
6.1 Early History of the El Tigre Project Area ............................................................61
6.2 History of El Tigre Ownership ..............................................................................65
6.3 Modern Exploration Programs ...............................................................................65
6.3.1 Anaconda .............................................................................................66
6.3.1.1 Anaconda Mapping ..................................................................66
6.3.1.2 Anaconda Geochemical Data ...................................................66
6.3.1.3 Anaconda Drill Data ................................................................69
6.3.2 Minera de Cordilleras 1995 .................................................................71
6.3.3 El Tigre Silver Exploration 2008 to 2012 ............................................71
6.3.3.1 2008 - 2009 Exploration Programs ..........................................71
6.3.3.2 2010 Exploration Program .......................................................74
6.3.3.3 2011 Exploration Program .......................................................75
6.3.3.4 2012 Exploration Program .......................................................76
6.3.4 El Tigre Silver Drilling Programs 2011 to 2013 ..................................77
6.3.4.1 El Tigre 2011 Drilling ..............................................................77
6.3.4.2 El Tigre 2012 Drilling ..............................................................79
6.3.4.3 El Tigre 2013 Exploration Drilling ..........................................80
6.3.4.4 Tailings Impoundment Drilling 2011 and 2013.......................83
6.3.5 Oceanus Exploration 2016 to 2019 ......................................................83
6.3.5.1 2016 IP Geophysical Survey Program .....................................83
6.3.5.2 2017 Underground Channel Program ......................................86
6.3.5.3 2018 Exploration Program .......................................................86
6.3.5.4 2019 Underground Channel Sample Program .........................90
6.3.6 Oceanus Drilling 2016-2017 ................................................................93
6.4 Historical Resource Estimates .............................................................................101
6.5 Historical Mining .................................................................................................102
7.0 GEOLOGICAL SETTING AND MINERALIZATION .................................................103
7.1 Regional Geology ................................................................................................103
7.2 Local Geology ......................................................................................................104
7.3 Local and Property Geology ................................................................................107
7.3.1 Stratigraphy ........................................................................................107
7.3.1.1 Granite (PCgr) ........................................................................107
7.3.1.2 Nodular Formation (Tn) .........................................................107
7.3.1.3 Fragmental Andesite (Tfa) .....................................................108
7.3.1.4 Flat Formation (Tf) ................................................................108
7.3.1.5 Cliff Formation (Tc) ..............................................................109
7.3.1.6 Tuff Formation (Ttf) ..............................................................109
7.3.1.7 Tigre Formation (Ttg) ............................................................109
7.3.1.8 Quartz Rhyolite Formation (Tgr) ...........................................110
7.3.1.9 Agglomerate Formation .........................................................110
7.3.1.10 Quartz Mica Rhyolite Tuff (Tgmr) ........................................110
P&E Mining Consultants Inc. Page ii
Silver Tiger Metals Inc., El Tigre Pre-Feasibility and Preliminary Economic Assessment, Report No. 481
7.3.1.11 Intrusive Rocks ......................................................................111
7.3.1.12 Tabular Formation .................................................................111
7.3.1.13 Andesite .................................................................................111
7.3.2 Structure .............................................................................................112
7.4 Deposit Geology and Mineralization ...................................................................112
7.4.1 Geological Controls ...........................................................................119
7.4.2 Alteration .........................................

[Excerpt trimmed for readability. Open the original source for the complete filing or document.]